Datacenter power work Tuesday, 1/11/05.

Fri Jan 7 15:28:21 PST 2005 — Datacenter power work Tuesday, 1/11/05. PG&E will be replacing the transformer for our building at 8 AM Tuesday. We are renting a generator to provide power to the building during the work period. Customers should see no change in service during this work. The datacenter itself is on UPS, and if the rental generator fails, our own standby generator will take over. Our tech support systems have their own UPS’s, so those friendly folks can always be there to help. -Russ and John