This Saturday (6/9) starting at 5AM, one of the San Francisco data centers we collocate equipment, will be performing a planned power maintenance. Although we have been assured by the colocation provider this work will be non-impactful, we have taken additional preparations to verify redundancy on all critical hardware, and will have a network engineer on site as a fail-safe.  The maintenance window officially extends until 6PM, and we will provide update when all work is completed.

– Network Engineering

(Update 8:12am) – We had a Power supply fail in a piece of our equipment during the first phase of the datacenter power maintenance.  We quickly swapped out the cabling to restore the unit.  Legacy DSL customers would have been impacted but service should now be restored.

 

Update(1:03pm) Power maintenance complete.